Project Description

Pharmaceutical Plant- Dublin

Project Details

Client (Confidential)
Tonnage 1000 T
Main Contractor PJ Hegarty
Engineer McElroy Associates Consulting Engineers

Project Description

Working with McElroy Associates consulting engineers and PJ Hegarty, Wall Steel erected 1000 tonnes of steel in various blocks. Metal decking and shear studs were also included in our package

Wall steel completed new Manufacturing, Administration and Research & Developments blocks for a Pharmaceuticals Plant in Blanchardstown Dublin.

Contract included Structural steel fabrication and erection (including connection design). Metal decking and shear studding and intumescent paint.

Along with primary structural steel frames, Wall Steel completed plant platforms, enclosures, and access walkways and pipe racks.