Tesco Extra & Retail Units, Maynooth, Co. Kildare
Summary:
Tonnage: 2800 tonnes of Structural steel & 12,000 m of floor decking
Detail:
Main Contractor: Precision Construction
Architect: Joseph Doyle & Associates
Engineer: Niall Fitzsimons & Co.
Wall Steel Project Manager: JJ Ward
Project Details:
This project included the supply and erection of 2800 tonnes of structural steel for the Tesco Extra store and retail units. Wall Steel also supplied and fitted 12,000 metres of floor decking and shear studding to fit out the first floor of the main building.
We worked closely with the main contractor to ensure the programme was met. This involved up to 25 operatives and 5 mobile cranes onsite. The contract was delivered safely and on time.